Module 2: Bids, Estimates & Contracts
Core promise: By the end of this module, you can take a bid request from the first message to a signed contract. You'll collect and compare subcontractor quotes, build a clean proposal from the contractor's numbers, follow up on time, and prepare contracts and purchase orders for signature.
Request → Quote → Proposal → Follow up → Contract → Order
An important boundary: The contractor sets the prices and makes the decisions. Your job is to organize the information, prepare the documents, and make sure nothing falls through the cracks.
In this module
- The Bid Process and Your Role
- Reading a Scope of Work
- Collecting and Comparing Sub Quotes
- Building the Proposal
- The Bid Log and Follow-Up
- Contracts and Subcontractor Agreements
- Purchase Orders
- Hands-On Exercises
- Knowledge Check
Module learning objectives
By the end of this module, you will be able to:
- Describe each step of the bid process and what you do at each one.
- Read a scope of work and write questions that close the gaps.
- Collect subcontractor quotes and compare them side by side.
- Build a complete proposal from the contractor's numbers and proofread it.
- Keep a bid log and send follow-ups on a steady schedule.
- Prepare contracts, subcontracts, and purchase orders for review and signature.
Lesson 2.1: The Bid Process and Your Role
A bid is a chain of small steps, and most of them are admin work. That's good news for you: the contractor does the thinking and pricing, and you keep everything moving.
| Step | Who leads | Where you help |
|---|---|---|
| 1. Request comes in | Contractor | Log it in the bid log, save the plans and notes to a project folder, and book the site visit. |
| 2. Review the scope | Contractor | Read the scope and write down questions and gaps for the contractor. |
| 3. Request sub quotes | Contractor decides who | Send quote requests, chase replies, and file the quotes. |
| 4. Build the estimate | Contractor | Compare quotes side by side and organize the numbers. |
| 5. Send the proposal | Contractor approves | Build the document from the contractor's numbers, proofread, and send it. |
| 6. Follow up | You, with the contractor's blessing | Send check-ins on a schedule and report what you hear. |
| 7. Contract signed | Owner and contractor | Prepare the contract, send it for e-signature, and file the signed copy. |
Lesson 2.2: Reading a Scope of Work
The scope of work is the heart of a bid. It says exactly what the contractor will do, and just as important, what they won't. Most disputes later come from a scope that was vague. Reading it carefully is one of the most valuable things you can do.
What a good scope includes
- Inclusions: the work and materials that are part of the price.
- Exclusions: what is not included, such as appliances or flooring repairs.
- Allowances: placeholder amounts for items not yet chosen.
- Assumptions: conditions the price depends on, such as "existing plumbing is in good condition."
How to spot gaps
As you read, ask: who supplies this, who installs it, and is it included in the price? Any item where the answer isn't clear goes on a list of questions for the contractor. You are not changing the scope. You are making sure it's complete before it reaches the owner.
Example: a scope with gaps
Remodel the Hartley kitchen per the drawings. Includes demolition, new cabinets, quartz countertops, tile backsplash, new lighting, and painting. Plumbing fixtures to be selected.
Notice what's unclear: who pays for the fixtures, whether the permit is included, who hauls away debris, and what "painting" covers. You'll write the questions yourself in the exercises.
Lesson 2.3: Collecting and Comparing Sub Quotes
Before the contractor can price a job, they need quotes from the subs who will do parts of it. You request them, chase them, and organize them.
What to include when you request a quote
- The project name, address, and the contractor's contact.
- The scope for that trade, with the drawings attached.
- The date you need the quote by, and the expected project timeline.
- A request that the quote list inclusions, exclusions, and how long the price is valid.
- A request for their license number and certificate of insurance.
Level the quotes
Quotes rarely cover the same things, so the lowest price isn't always the lowest cost. Leveling means putting the quotes in one table with the same rows so differences are easy to see. The contractor chooses. You make the choice easy to make.
| Item | Delgado Plumbing | Harbor Plumbing | Northside Plumbing |
|---|---|---|---|
| Price | $7,200 | $6,400 | $7,650 |
| Move sink, install fixtures | Yes (fixtures supplied by owner) | Yes (fixtures supplied by owner) | Yes (includes $900 fixture allowance) |
| New gas line for range | Included | Not included | Included |
| Permit fee | Included | Not included | Included |
| Quote valid for | 30 days | 14 days | 45 days |
| License and insurance attached | Yes | Insurance missing | Yes |
Harbor's price looks lowest, but it leaves out the gas line and the permit fee, so the real cost would be higher. That's the kind of difference your table makes visible.
Lesson 2.4: Building the Proposal
The proposal is the document the owner reads before deciding. It should be clear, accurate, and complete. You build it from the contractor's scope, numbers, and terms.
The parts of a proposal
- Company information: name, address, phone, email, and license number.
- Owner and project information: owner names, job site address, date, and proposal number.
- Scope of work: what's included.
- Exclusions and allowances: what's not included and the placeholder amounts.
- Price and payment schedule: the total and when payments are due.
- Timeline: the estimated start date and duration.
- Terms: how changes are handled, warranty details, and how long the proposal is valid.
- Signature lines for the owner and the contractor.
Example: the Hartley payment schedule
| Payment | When | Percent | Amount |
|---|---|---|---|
| Deposit | At signing | 10% | $4,850 |
| Progress payment 1 | After the rough inspection passes | 30% | $14,550 |
| Progress payment 2 | When the cabinets are installed | 30% | $14,550 |
| Final payment | After the punch list is complete | 30% | $14,550 |
| Total | 100% | $48,500 |
Rules about deposits and payment schedules vary by location, so always use the contractor's approved terms. You'll see this same schedule again when you bill the Hartley job in Module 6.
Proofreading checklist
- Owner names and job site address are spelled correctly.
- The payment schedule adds up to the total price.
- The scope matches the contractor's notes and the sub quotes.
- Exclusions and allowances are listed.
- The proposal shows how long it's valid.
- The file is named clearly, for example "Hartley Kitchen Proposal v1."
Lesson 2.5: The Bid Log and Follow-Up
Most bids that go quiet aren't lost. The owner is busy. A steady, polite follow-up wins more work than almost anything else a contractor can do, and it's exactly the task contractors forget.
The bid log
A bid log is a simple spreadsheet with one row per bid. It tells the contractor, at a glance, where every bid stands.
| Project | Client | Sent | Amount | Status | Next step |
|---|---|---|---|---|---|
| Hartley kitchen remodel | Priya and Tom Hartley | Mar 3 | $48,500 | Awaiting response | Follow up Mar 6 |
| Okafor bathroom update | Ngozi Okafor | Feb 24 | $18,200 | Follow-up sent | Check in Mar 10 |
| Lindgren deck rebuild | Sam Lindgren | Feb 10 | $22,900 | No response | Ask Marcus to close out |
A follow-up schedule
| When | What to do |
|---|---|
| 2 to 3 days after sending | Confirm they received it and offer to answer questions. |
| About 1 week | Send a short check-in and mention when the proposal expires. |
| About 2 weeks | Send a final check-in and ask whether they'd like to move forward or pause. |
| After that | Mark the bid "No response," tell the contractor, and let them decide whether to call. |
Sample follow-up messages
Day 3
Subject: Your kitchen remodel proposal
Hi Priya and Tom,
I'm following up for Marcus at Ridgeline Builders to make sure you received the proposal for your kitchen remodel. If you have questions about the scope or pricing, I'm happy to pass them to Marcus or set up a time to talk.
Thank you,
[Your name]
About 1 week
Subject: Checking in on your kitchen proposal
Hi Priya and Tom,
Just checking in on the proposal Marcus sent. It's valid through [date]. If you'd like to adjust anything or talk it through, let me know and I'll set it up.
Thank you,
[Your name]
Lesson 2.6: Contracts and Subcontractor Agreements
Once an owner says yes, the proposal becomes a contract. Contractors work with two kinds of agreements.
| Agreement | Between | Purpose |
|---|---|---|
| Owner contract | The owner and the general contractor | Defines the project, the price, the payment schedule, and how changes are handled. |
| Subcontract | The general contractor and a subcontractor | Defines that sub's work, price, schedule, and insurance requirements. |
What these agreements usually contain
- Names and addresses of both parties.
- The scope of work, matching the approved proposal or quote.
- The price and payment terms.
- The schedule, including the start date.
- How change orders are handled.
- Insurance requirements (mainly in subcontracts).
- Warranty terms and signature lines.
Your role
You prepare the document from the contractor's approved template, fill in the details, check it against the proposal or quote, send it for e-signature, and file the signed copy. Common e-signature tools include DocuSign, Dropbox Sign, PandaDoc, and Adobe Sign.
Pre-send checklist
- Names and addresses are spelled correctly.
- The scope matches the approved proposal or quote.
- The price and payment schedule match exactly.
- Dates make sense (for example, the start date comes after the permit is expected).
- Insurance requirements and any attachments are included.
- Signature blocks exist for every party.
Lesson 2.7: Purchase Orders
A subcontract hires a business to do work. A purchase order (PO) orders materials or products from a supplier. It's a short, specific document that leaves no room for misunderstanding about what is being ordered.
What a purchase order includes
- A PO number, so everyone can refer to the same order.
- The date, the supplier, and the project it's for.
- Items, quantities, and prices.
- The delivery date and delivery address.
- A contact person and payment terms.
Example: the Hartley cabinets
Purchase Order #1001
Date: [date]
Supplier: Oakline Cabinets
Project: Hartley kitchen remodel, [job site address]
Items: Kitchen cabinet package per approved drawing: 8 base, 5 wall, 1 pantry; shaker style, white
Price: $11,200
Delivery: [date], to the job site
Contact: Marcus Webb, Ridgeline Builders
Please confirm this order and the delivery date in writing.
Cabinets are a long-lead item, so the order goes in early. After sending a PO, save the supplier's confirmation and compare the delivery date to the schedule. If the date slips, tell the contractor right away.
Lesson 2.8: Hands-On Exercises
Try each exercise on your own first. Then open the self-check answers to compare.
Exercise 1: Spot the scope gaps
Here is the scope of work again:
Remodel the Hartley kitchen per the drawings. Includes demolition, new cabinets, quartz countertops, tile backsplash, new lighting, and painting. Plumbing fixtures to be selected.
Write five questions you'd send to Marcus before this scope goes into the proposal.
Self-check answers
Any five of these are good:
- Who supplies the plumbing fixtures, and should there be an allowance for them?
- Is the permit fee included in the price?
- Is debris removal (a dumpster) included?
- What does "painting" cover: walls only, or ceiling and trim too?
- Who handles flooring repairs after the old cabinets come out?
- What are the quartz color, edge, and thickness?
- Who supplies and installs the appliances?
- Is the new gas line for the range included?
Exercise 2: Level the quotes
Marcus received three electrical quotes for the Hartley kitchen. Compare them, then write what differs and three questions you'd ask.
| Item | Brightline Electric | Volt & Co | Sparks Bros |
|---|---|---|---|
| Price | $6,800 | $5,900 | $6,350 |
| Island outlet and new lighting circuits | Included | Included | Included |
| Permit fee | Included | Not included | Included |
| Panel work | Panel check included | Not included | Panel check included |
| Light fixtures | Installs owner-supplied | Includes $500 allowance | Installs owner-supplied |
| Insurance certificate | Attached | Attached | Not attached |
| Quote valid for | 30 days | 30 days | 14 days |
Self-check answers
What differs: Volt & Co is cheapest, but it leaves out the permit fee and panel work. Sparks Bros hasn't sent proof of insurance, and its quote expires in 14 days. Brightline includes the most and has its paperwork in order. Fixtures are handled differently: Volt includes an allowance, while the others install owner-supplied fixtures.
Questions to ask:
- Volt & Co: what would the permit fee and any panel work cost?
- Sparks Bros: can you send your certificate of insurance and license?
- All three: can you confirm who supplies the fixtures, so the quotes compare fairly?
Important: you don't pick the winner. You prepare the comparison and the questions, and Marcus decides.
Exercise 3: Write the follow-up
Marcus sent the Hartleys their proposal four days ago, and they haven't replied. Write a short follow-up email from Marcus's office.
Sample answer
Subject: Checking in on your kitchen proposal
Hi Priya and Tom,
I'm following up for Marcus at Ridgeline Builders to make sure the proposal for your kitchen remodel reached you. If you have any questions about the scope or pricing, I can pass them along or set up a quick call with Marcus.
The proposal is valid through [date].
Thank you,
[Your name]
What makes it work: it's short, friendly, and offers help without pressure. It also shows the expiration date, which gently signals timing. It does not offer a discount or change the terms, because that's Marcus's call.
Exercise 4: Catch the contract errors
Below are the approved proposal details and the draft contract you were asked to prepare. Find the five mistakes before it goes out.
| Item | Approved proposal | Draft contract |
|---|---|---|
| Owners | Priya and Tom Hartley | Priya and Tom Hartly |
| Price | $48,500 | $45,800 |
| Countertops | Quartz | Laminate |
| Start date | After permit approval (expected May 12) | May 5 |
| Signature blocks | Owners and Ridgeline Builders | Owners only |
Self-check answers
- The owners' last name is misspelled ("Hartly").
- The price has transposed digits: $45,800 instead of $48,500.
- The countertop material says laminate instead of quartz.
- The start date (May 5) is before the permit is expected (May 12).
- The contract has no signature block for Ridgeline Builders.
What to do: fix the spelling and signature block. For the price, material, and start date, confirm with Marcus before changing anything, because those affect the deal. Then send the corrected contract for signature.
Exercise 5: Prepare the purchase order
Marcus says: "Order the cabinets from Oakline. 8 base, 5 wall, 1 pantry, shaker style, white. $11,200. Have them delivered the week before install, to the Hartley job site."
List the fields your purchase order needs, and flag anything you'd need to ask Marcus before sending it.
Self-check answers
Fields: PO number, date, supplier (Oakline Cabinets), project (Hartley kitchen remodel), items and quantities (8 base, 5 wall, 1 pantry, shaker style, white), price ($11,200), delivery date and address, contact person, and payment terms.
Missing information to ask Marcus about:
- The exact delivery date. "The week before install" needs the install date to calculate.
- The job site address, if it's not already in the project folder.
- The payment terms with Oakline.
Once you have those, send the PO, ask Oakline to confirm in writing, and compare their delivery date to the schedule.
Lesson 2.9: Knowledge Check
Answer each question in your own words, then check yourself.
- Who sets the price in a bid, and what is your role?
- Why shouldn't you recommend the lowest sub quote without leveling the quotes first?
- Name four things every proposal should include.
- What's the difference between a subcontract and a purchase order?
- When should you flag a request to the contractor instead of fixing it yourself?
Self-check answers
- The contractor sets the price. Your role is to organize the information, prepare documents from their numbers, and keep the process moving.
- Quotes often cover different things, so the lowest price may leave out items that will cost extra. Leveling shows the real differences.
- Any four of: company information, owner and project information, scope of work, exclusions and allowances, price and payment schedule, timeline, terms, and signature lines.
- A subcontract hires a business to do work. A purchase order orders materials or products from a supplier.
- Any time a change touches legal wording, price, scope, or dates. Typos and formatting you can fix. Anything that changes the deal goes to the contractor.
Before you move on
You're ready for Module 3 when you can say yes to each of these:
- I can read a scope of work and list the gaps.
- I can request, chase, and compare sub quotes.
- I can build and proofread a proposal from the contractor's numbers.
- I can keep a bid log and follow up on a schedule.
- I can prepare a contract or purchase order and check it before sending.